FAQs | Contact Us | Search

Home About Eastfield Future Students Current Students Continuing Education Business/Community Employees Español  
Schedules Admissions & Registration  |  Library  |  Academics  |  Athletics  |  eConnect  |  eCampus  |  Catalog

Eastfield College
Construction Team Meeting

Minutes
Wednesday, July 9, 2008

Committee Members

Staff Members

 

Arrowood, Dan
Booth, Johnny
Buck, Lonney
James, Darren
Johnson, Michael
Liston, Scott
Littleton, Dave
Moore, Dustin
Napier, Brad
Starling, Jim
Terrell, Allen
Westbrook, Brad

Backman, Lisa
Bueno, Esther
Cinclair, Richard
Criswell, John
Gonzales, Lucinda
Grigsby, Lindle
Hansen, Susan
Horak, Michael
Kozlowski, Gerald

Marrero, Mike
Martin, James
Olguin, Javier
Ross, Ann
Sykes, Art
Thiehoff, Jack
Washington, Michael
Watts, Niki

Welcome and Introductions

The Construction Team council convened on Wednesday, July 9, 2008 at 8:53a.m.  Dr. Lindle Grigsby welcomed the members. 

Learning Studios

Dustin Moore with Rogers-O’Brien reported the masonry work on the west side of building has begun.  As the brick work is completed, going South and around the building, the stucco workers will begin following them.  The roof trusses’ has begun and will match the existing buildings on campus.  Interior framing on the first floor is basically complete and work has begun on the second floor.  The Learning Studios building is scheduled to be complete by mid to late November 2008.  The official opening ceremony will probably be held January 2009, no date has been selected. 

Dan Arrowood reported they are working closely with Rogers-O’Brien.

What information is needed to move forward?  Dustin Moore reported they have samples of “stained concrete” and will need input from Eastfield College Construction Team Members.

Center for Child and Parent Studies

Johnny Booth - Booth Architects and Dan Arrowood with HKS reported they expect site plans to be finalized by Friday, July 11, 2008.  The architectural site plans have been approved by the city of Mesquite.  The plan review is contingent upon the engineering review.  Guaranteed Maximum Price (GMP) meeting will be held Friday, July 11, 2008.

What information is needed to move forward?  No additional information is needed at this time.

Pleasant Grove Campus

Brad Napier, with Adolfson & Peterson reported the foundation pier drilling will begin on Monday, July 14, 2008.  Water and sewer lines are being installed.  Grading for the drives and parking areas is almost complete so this area can be framed for concrete.

What information is needed to move forward? No additional information is needed at this time.

Workforce / Criminal Justice Facility

Halff Associates reported the site plans are “nearly” complete.  The first review period has been executed.  The case manager with the city of Mesquite will follow-up in approximately two weeks on the plans that have been submitted.  The parking lot configuration is currently under discussion.

Susan Hansen reported they are working with A&P on a tentative schedule to discuss the water and sewer trench lines.  Dave Littleton reiterated the need of reminding the city of Mesquite about the “expedited review plans”.

Groundbreaking ceremony is scheduled for late July or early August 2008.

What information is needed to move forward? No additional information is needed at this time.

Technology “T” Building Expansion

Michael Johnson with Johnson McKibben Architectural firm reported 50% construction drawings have been submitted and pricing received.  95% drawings are to be delivered by July 29, 2008.  The site plan has been submitted to the city of Mesquite, a separate re-plat of an easement is required because of encroachment into the easement.

What information is needed to move forward?  No additional information is needed at this time.

Utility and Infrastructure Update

Dave Littleton with Halff Associates reported the revision to water line 3-plan will be submitted to the city of Mesquite today.  Will begin work upon approval from the city.

Art Sykes reported the contractor will attempt to have the Oates drive entrance assessable by Monday, July 14, 2008.  This is contingent upon building materials, i.e. concrete etc. being delivered on time.  Additional scheduled dates:

What is needed to move forward?  No additional information is needed at this time.

Perimeter Road

Representatives from Criado & Associates were not present at today’s meeting.  No additional information was reported since last month’s meeting.  A meeting is scheduled for next week with Craido and with Dave Littleton from Halff Associates on the La Prada entrance design.

Adaptive Remodel

Dr. Lindle Grigsby reported “work is continuing with the remodeling list from Eastfield.  The architects and contractors are to complete their contract negotiations with the Bond Program Managers this next week and be ready for another walk through to see the nature of the changes since their last preview.  Eastfield is still finalizing the list of remodeling projects.”

Parking Expansion

Dr. Lindle Grigsby reported Eastfield College expects to add approximately 150 to 200 parking spaces to be located near the Workforce/Criminal Justice and Center for Child & Parent Studies buildings.  Some parking spaces will be placed in the west area of campus. 

Furniture Team Visits

Jack Thiehoff reported all furniture have been selected for the Learning Studios building.    Manufacturers have been notified of the pending orders so they can begin assembling the materials needed and staffing for the order that will be coming. 

Dr. Lindle Grigsby and Susan Hansen will meet with Jack Thiehoff and Lucinda Gonzales immediately after today’s construction meeting to discuss the overall order.      

Key Dates

(Source of information provided by Dr. Lindle Grigsby)

Open Discussion

Reminder:

Future Team Meeting Dates:

August 6, 2008
September 3, 2008
October 8, 2008
November 5, 2008
December 3, 2008

Meeting adjourned 9:40a.m.

Ann Ross  
   Recorder     

Eastfield College | 3737 Motley Drive Mesquite, Texas 75150 | 972-860-7100 | Dallas County Community College District
Home | About Eastfield | Future Students | Current Students | Continuing Education | Employees | Español